Front | Back |
WPR | Work Performance Reports |
RFI | Request for Information |
TCO | Total Cost of Ownership |
VOIP | Voice Over Internet Protocol |
PB | Performance Baseline |
CPI | Cost Performance Index |
WPI | Work Performance Information |
PDM | Precedence Diagramming Method |
LRC | Learning Resource Center |
RACI | Responsible, Accountable, Consulted, Informed |
BCR | Benefit-Cost Ratio |
NDA | Non-Disclosure Agreement |
SPI | Schedule Performance Index |
VAC | Variance at Completion |
RBS | Resource Breakdown Structure |
PV | Planned Value |
AOB | Any Other Business |
EF | Early Finish |
TTT | Train-the-Trainer |
FPA | Function Point Analysis |
PMO | Project Management Office |
SDLC | System Development Life Cycle |
ES | Early Start |
MVP | Minimum Viable Product |
PMBOK | Project Management Body of Knowledge |
PERT | Program Evaluation and Review Technique |
CCB | Change Control Board |
EV | Earned Value |
CSF | Critical Success Factor |
WBS | Work Breakdown Structure |
LS | Late Start |
SV | Schedule Variance |
EAC | Estimate at Completion |
LF | Late Finish |
AC | Actual Cost |
TOR | Terms of Reference |
SIPOC | Suppliers, Inputs, Process, Outputs, Customers |
BPR | Business Process Reengineering |
ROI | Return on Investment |
CCB | Change Control Board |
WPD | Work Performance Data |
ETC | Estimate to Complete |
PMP | Project Management Professional |
CV | Cost Variance |