Free PMI Project Management Professional (PMP) Practice Question

A key supplier has announced a delay in their delivery schedule, which will impact the critical path of the project. As a project manager, what is your NEXT step to manage the impact on the project?

  • Reduce the project quality standards to maintain the schedule

  • Recommend adjustments to the project scope/backlog to accommodate the new delivery schedule

  • Ignore the delay since the supplier should catch up

  • Escalate the problem to the project sponsor as this deals with critical path

This question's topic:
PMI Project Management Professional (PMP) / 
Business Environment
Your Score:

Check or uncheck an objective to set which questions you will receive.