The correct answer is 3 days. Float, also known as slack, is the amount of time an activity can be delayed without affecting the project's overall schedule. It can be calculated using two formulas:
Float = Late Start (LS) - Early Start (ES)
Float = Late Finish (LF) - Early Finish (EF)
In this question, we are given the Early Start (ES) and Late Start (LS) values. Using the first formula:
Float = LS - ES Float = 8 - 5 Float = 3 days
This means the activity can be delayed by up to 3 days without impacting the project's completion date. Understanding float is crucial for project managers as it helps in prioritizing tasks, managing resources, and identifying potential schedule risks.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What are Early Start (ES) and Late Start (LS) in project management?
What does Float (slack) mean in project management?
How is Float calculated, and why is it important?