The correct answer is 3 days. Float, also known as slack, is the amount of time an activity can be delayed without impacting the project's overall schedule. It can be calculated using two formulas:
Float = Late Start (LS) - Early Start (ES)
Float = Late Finish (LF) - Early Finish (EF)
In this case, we are given the Early Start (ES) and Late Start (LS) values. Using the first formula:
Float = LS - ES Float = 8 - 5 Float = 3 days
This means the activity can be delayed by up to 3 days without affecting the project's critical path or end date. Understanding float is essential for project managers to prioritize tasks, allocate resources efficiently, and manage schedule risks.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What is the difference between Early Start (ES) and Late Start (LS)?
What does float mean in project management?
Why is it important to understand total float in project management?