Correct calculations are essential to monitor the project's progress. Earned Value (EV) is calculated by multiplying the Actual % Complete by the Budget at Completion (BAC). Using the given data: EV = 0.60 * $200,000 = $120,000.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does Earned Value (EV) mean in project management?
Open an interactive chat with Bash
How is Budget at Completion (BAC) calculated?
Open an interactive chat with Bash
What is the formula to calculate Earned Value (EV)?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
People
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features