Free PMI Project Management Professional (PMP) Practice Question
A project has a Budget at Completion (BAC) of $200,000. The Planned Value (PV) is $100,000, and the Earned Value (EV) is $80,000. What is the Schedule Performance Index (SPI) for this project?
The Schedule Performance Index (SPI) is calculated by dividing the Earned Value (EV) by the Planned Value (PV). In this scenario:
SPI = EV / PV = $80,000 / $100,000 = 0.8
An SPI of less than 1 indicates that the project is behind schedule, as it means the value of the work performed is less than the planned work at that point in time.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are the implications of having an SPI of less than 1?
Open an interactive chat with Bash
What is the difference between Planned Value (PV) and Earned Value (EV)?
Open an interactive chat with Bash
How do you calculate SPI, and why is it important?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
People
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features