Free PMI Project Management Professional (PMP) Practice Question
A project has a Budget at Completion (BAC) of $200,000. The project is currently 40% complete, with an Actual Cost (AC) of $85,000 and a Planned Value (PV) of $90,000. What is the Schedule Variance (SV) of the project?
To calculate the Schedule Variance (SV), we need to find the Earned Value (EV) and the Planned Value (PV). EV is calculated as the Actual % Complete multiplied by the Budget at Completion (BAC): EV = 40% x $200,000 = $80,000. Schedule Variance (SV) is then calculated as EV - PV: SV = $80,000 - $90,000 = -$10,000. The negative variance indicates the project is behind the planned schedule.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Earned Value (EV) and how is it calculated?
Open an interactive chat with Bash
What is Planned Value (PV) and why is it important?
Open an interactive chat with Bash
What does a negative Schedule Variance (SV) indicate?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
People
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features