A project has a Budget at Completion (BAC) of $200,000. The project is currently 40% complete according to the project schedule, but the actual work performed indicates an earned value (EV) of $70,000. What is the Schedule Variance (SV)?
-$70,000
-$10,000
$70,000
$10,000