Free PMI Project Management Professional (PMP) Practice Question
A project has a Budget at Completion (BAC) of $500,000, Earned Value (EV) of $200,000, and Actual Cost (AC) of $250,000. What is the To-Complete Performance Index (TCPI) based on the BAC?
The correct answer is 1.2. To calculate the TCPI based on BAC, we use the formula: TCPI = (BAC - EV) / (BAC - AC). Plugging in the values: TCPI = (500,000 - 200,000) / (500,000 - 250,000) = 300,000 / 250,000 = 1.2. This result indicates that the project team needs to achieve a cost performance index of 1.2 for the remaining work to complete the project within the original budget (BAC). A TCPI greater than 1 suggests that the project is currently over budget, and the team needs to improve their cost efficiency to meet the BAC target.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What is Earned Value (EV) in project management?
What does BAC stand for and why is it important?
How do you interpret the To-Complete Performance Index (TCPI)?
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features