Free PMI Project Management Professional (PMP) Practice Question

A project has a Budget at Completion (BAC) of $500,000, Earned Value (EV) of $200,000, and Actual Cost (AC) of $250,000. What is the To-Complete Performance Index (TCPI) based on the BAC?

  • 1.5

  • 0.6

  • 0.8

  • 1.2

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.