Free PMI Project Management Professional (PMP) Practice Question

A project has a Budget at Completion (BAC) of $500,000. The current Actual Cost (AC) is $300,000, and the Cost Performance Index (CPI) is 0.75. What is the Estimate to Complete (ETC)?

  • $200,000

  • $366,667

  • $400,000

  • $566,667

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.