Free PMI Project Management Professional (PMP) Practice Question

A project has a Budget at Completion (BAC) of $500,000. The current Estimate at Completion (EAC) is calculated to be $450,000. How much is the Variance at Completion (VAC) for this project?

  • $950,000

  • $450,000

  • $50,000

  • Zero

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.