A project has a Budget at Completion (BAC) of $500,000. The current Estimate at Completion (EAC) is calculated to be $450,000. How much is the Variance at Completion (VAC) for this project?
The Variance at Completion (VAC) is calculated by subtracting the Estimate at Completion (EAC) from the Budget at Completion (BAC). In this case, VAC = BAC - EAC = $500,000 - $450,000 = $50,000. This positive value indicates that the project is expected to be under budget by $50,000. The other options provided may include common calculation errors or misunderstandings of the formula.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does BAC mean in project management?
Open an interactive chat with Bash
How is EAC calculated?
Open an interactive chat with Bash
Why is a positive VAC important?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
People
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features