A project has a Budget at Completion (BAC) of $500,000. The project has spent $200,000 to date (AC) and has realized an Earned Value (EV) of $160,000. If the project management intends to meet the original budget goals, what is the To-Complete Performance Index (TCPI)?

  • 1.00

  • 1.13

  • 0.80

  • 1.25