A project manager calculates a key performance metric by dividing Earned Value by Actual Cost. The result is 0.85. What does this value indicate about the project's financial status?

  • The project is over budget

  • The project is exactly on budget

  • The calculated value is inconclusive without additional information

  • The project is under budget