Free PMI Project Management Professional (PMP) Practice Question

A project manager calculates the Schedule Performance Index (SPI) and finds it to be 0.85. What does this value indicate about the project's schedule performance?

  • The project is behind schedule

  • The project is exactly on schedule

  • The project is 85% complete

  • The project is ahead of schedule

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.