Free PMI Project Management Professional (PMP) Practice Question

A project manager has established team ground rules and communicated them to the team and external stakeholders. However, they notice that some team members consistently violate these rules. What is the most appropriate action for the project manager to take?

  • Escalate the issue to higher management for disciplinary action

  • Privately discuss the violations with the individual team members and reiterate the importance of adherence

  • Ignore the violations to avoid confrontation and maintain team harmony

  • Publicly call out the team members who violated the rules during a team meeting

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.