Free PMI Project Management Professional (PMP) Practice Question

A project manager has identified that a critical risk has become an issue that threatens the project's timeline. Which of the following actions should the project manager prioritize to manage this issue effectively?

  • Allocate additional resources to the project and then inform stakeholders of the solution

  • Collaborate with relevant stakeholders on the approach to resolve the issue

  • Postpone addressing the issue until the next project phase

  • Modify the project scope to exclude the deliverables affected by the issue

This question's topic:
PMI Project Management Professional (PMP) / 
Process