Free PMI Project Management Professional (PMP) Practice Question

A project manager is analyzing the network diagram for a construction project. Activity X has a duration of 5 days and must be completed before the project can finish. If the project must be completed in 20 days, what is the Late Start (LS) for Activity X?

  • 5 days

  • 15 days

  • 10 days

  • 20 days

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.