Free PMI Project Management Professional (PMP) Practice Question

A project manager is analyzing the schedule for a construction project. Activity X has an Early Start (ES) of Day 10 and a Late Start (LS) of Day 15. What does this information indicate about Activity X?

  • Activity X must start on Day 15

  • Activity X is on the critical path

  • Activity X has a duration of 5 days

  • Activity X has 5 days of float

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.