A project manager is analyzing the schedule for a construction project. Activity X has an Early Start (ES) of Day 10 and a Late Start (LS) of Day 15. What does this information indicate about Activity X?
Activity X must start on Day 15
Activity X is on the critical path
Activity X has a duration of 5 days
Activity X has 5 days of float