A project manager is assessing risks for a new software development project. Risk A has a probability of 0.4 and an impact of 0.5, while Risk B has a probability of 0.6 and an impact of 0.3. Which risk should the project manager prioritize?
Both risks equally
The risk with the highest probability
Risk B
Risk A