Free PMI Project Management Professional (PMP) Practice Question

A project manager is calculating the Earned Value (EV) for a project that has a Budget at Completion (BAC) of $500,000. The project is currently 40% complete. What is the Earned Value?

  • $200,000

  • $250,000

  • $400,000

  • $300,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.