Free PMI Project Management Professional (PMP) Practice Question
A project manager is calculating the Earned Value (EV) for a project that has a Budget at Completion (BAC) of $500,000. The project is currently 40% complete. What is the Earned Value?
The correct answer is $200,000. Earned Value (EV) is calculated by multiplying the actual percentage of work completed by the Budget at Completion (BAC). In this case, EV = Actual % Complete x BAC = 40% x $500,000 = 0.40 x $500,000 = $200,000. This value represents the budgeted cost of work performed to date, providing a measure of the value of completed work in terms of the original budget.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Earned Value (EV) in project management?
Open an interactive chat with Bash
What does Budget at Completion (BAC) mean?
Open an interactive chat with Bash
How do you calculate Earned Value (EV)?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features