Free PMI Project Management Professional (PMP) Practice Question

A project manager is calculating the Late Finish (LF) for an activity. The Late Start (LS) is day 15, and the activity duration is 7 days. What is the Late Finish for this activity?

  • 21 days

  • 22 days

  • 20 days

  • 23 days

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.