A project manager is calculating the Late Finish (LF) for an activity. The Late Start (LS) is Day 10, and the activity duration is 5 days. What is the Late Finish for this activity?
The correct answer is Day 14. The formula for calculating Late Finish (LF) is: LF = LS + Duration - 1. In this case, LS = 10 and Duration = 5. Therefore, LF = 10 + 5 - 1 = 14. It's important to note that we subtract 1 from the result because the activity starts on Day 10 and ends on Day 14, which is a total of 5 days. If we didn't subtract 1, we would incorrectly count 6 days instead of 5. This calculation is crucial for determining the latest an activity can finish without delaying the project end date.
Learn More
AI Generated Content may display inaccurate information, always double-check anything important.
What is Late Start (LS) in project management?
What does the term 'activity duration' mean?
Why do we subtract 1 when calculating Late Finish from Late Start and duration?