Free PMI Project Management Professional (PMP) Practice Question

A project manager is calculating the Late Finish (LF) for an activity. The Late Start (LS) is Day 10, and the activity duration is 5 days. What is the Late Finish for this activity?

  • Day 16

  • Day 15

  • Day 13

  • Day 14

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.