Free PMI Project Management Professional (PMP) Practice Question

A project manager is estimating the duration of a task with the following data: Optimistic time = 8 days, Most Likely time = 12 days, and Pessimistic time = 20 days. The Expected Duration (TE) of the task is 15 days.

  • False

  • True

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.