Free PMI Project Management Professional (PMP) Practice Question

A project manager is estimating the duration of an activity. The optimistic estimate is 6 days, the most likely estimate is 10 days, and the pessimistic estimate is 20 days. The expected duration using the PERT (Program Evaluation and Review Technique) formula is 11 days.

  • True

  • False

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.