A project manager is estimating the monetary impact that identified risks will have on the project to assist in decision-making for their risk responses. Which technique is the project manager using?
Decision Tree Analysis
Qualitative Risk Analysis
Expected Monetary Value Analysis
Monte Carlo Simulation