Free PMI Project Management Professional (PMP) Practice Question

A project manager is estimating the monetary impact that identified risks will have on the project to assist in decision-making for their risk responses. Which technique is the project manager using?

  • Monte Carlo Simulation

  • Qualitative Risk Analysis

  • Decision Tree Analysis

  • Expected Monetary Value Analysis

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.