A project manager is estimating the monetary impact that identified risks will have on the project to assist in decision-making for their risk responses. Which technique is the project manager using?

  • Decision Tree Analysis

  • Qualitative Risk Analysis

  • Expected Monetary Value Analysis

  • Monte Carlo Simulation