A project manager is evaluating two potential projects using the Internal Rate of Return (IRR) method. Project A has an IRR of 15%, while Project B has an IRR of 18%. The company's required rate of return is 16%. Based on this information, which project should the project manager recommend?

  • Neither project

  • Project B

  • Both projects equally

  • Project A