A project manager is faced with a sudden change in project scope that requires additional resources. However, the project budget is limited, and the manager must make a decision on how to proceed. Which of the following is the BEST course of action?
Request additional budget to hire more resources
Prioritize the project tasks and allocate resources accordingly
Overallocate existing resources to complete the additional work
Reallocate resources from other projects to meet the new requirements