Free PMI Project Management Professional (PMP) Practice Question

A project manager is initiating a high-stakes project involving cross-functional team members from disparate regions. To ensure a high standard of communication, which action is most appropriate for effectively establishing and maintaining adherence to team ground rules during the project kickoff?

  • Implement ground rules without formal announcement, expecting team members to adhere through observation of others.

  • Send an email detailing the ground rules after the kickoff meeting.

  • Delegate to team leaders to convey these ground rules to their subordinates to streamline communication.

  • Formally document and present the ground rules in the kickoff meeting, ensuring all members receive the same information.

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.