Free PMI Project Management Professional (PMP) Practice Question

A project manager is leading a high-risk, cross-functional project within an organization that has a well-established, centralized governance framework. Which of the following would be the most appropriate approach for the project manager to take when determining the project's governance structure?

  • Align the project's governance structure with the organization's centralized governance framework while incorporating additional oversight measures to address the project's high-risk nature

  • Establish a project-specific governance structure that operates independently from the organization's governance framework

  • Implement a completely autonomous governance structure that allows the project team to make decisions without external oversight

  • Replicate the organization's centralized governance structure without any modifications for the project