A project manager is managing a large, distributed team working across multiple time zones. The complexity of the project requires frequent updates, collaborative decision-making, and immediate clarity on issues as they arise. Which of the following communication methods is best suited for achieving these needs?
Synchronous web conferencing
Casual, informal verbal updates during team members' work hours
Formal written reports distributed weekly
Asynchronous communication through email