A project manager is managing a large, distributed team working across multiple time zones. The complexity of the project requires frequent updates, collaborative decision-making, and immediate clarity on issues as they arise. Which of the following communication methods is best suited for achieving these needs?

  • Formal written reports distributed weekly

  • Synchronous web conferencing

  • Casual, informal verbal updates during team members' work hours

  • Asynchronous communication through email