A project manager is nearing the end of a project. What is the BEST action to take to ensure the project or phase is closed properly?
Release all project team members and inform stakeholders that the project is completed.
Conduct a final project performance report review and obtain formal acceptance of the project deliverables from the customer.
Begin the next project.
Archive all project documents.