A project manager is nearing the end of a project. What is the BEST action to take to ensure the project or phase is closed properly?
Begin the next project.
Release all project team members and inform stakeholders that the project is completed.
Archive all project documents.
Conduct a final project performance report review and obtain formal acceptance of the project deliverables from the customer.