A project manager is reviewing the current project status and needs to forecast the total cost at completion. The project has a Budget at Completion (BAC) of $500,000, current Actual Cost (AC) of $200,000, and an Earned Value (EV) of $180,000. Assuming the current cost performance trend will continue, what is the Estimate at Completion (EAC)?
$500,000
$555,556
$540,000
$520,000