Free PMI Project Management Professional (PMP) Practice Question

A project manager is reviewing the current project status and needs to forecast the total cost at completion. The project has a Budget at Completion (BAC) of $500,000, current Actual Cost (AC) of $200,000, and an Earned Value (EV) of $180,000. Assuming the current cost performance trend will continue, what is the Estimate at Completion (EAC)?

  • $500,000

  • $555,556

  • $540,000

  • $520,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.