A project manager is reviewing the Earned Value Management data for their project. The Budget at Completion (BAC) is $500,000, and the current Earned Value (EV) is $200,000. The Actual Cost (AC) to date is $250,000. What is the Cost Performance Index (CPI) for this project?
0.5
1.25
0.8
2.0