Free PMI Project Management Professional (PMP) Practice Question

A project manager is reviewing the Earned Value Management data for their project. The Budget at Completion (BAC) is $500,000, and the current Earned Value (EV) is $200,000. The Actual Cost (AC) to date is $250,000. What is the Cost Performance Index (CPI) for this project?

  • 0.5

  • 1.25

  • 0.8

  • 2.0

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.