A project manager is reviewing the financial performance of a project. The Budget at Completion (BAC) is $500,000, and the current Estimate at Completion (EAC) is $480,000. What is the Variance at Completion (VAC) for this project?
$20,000
-$20,000
$980,000
$120,000