Free PMI Project Management Professional (PMP) Practice Question

A project manager is reviewing the financial performance of a project. The Budget at Completion (BAC) is $500,000, and the current Estimate at Completion (EAC) is $480,000. What is the Variance at Completion (VAC) for this project?

  • $20,000

  • $120,000

  • -$20,000

  • $980,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.