Free PMI Project Management Professional (PMP) Practice Question

A project manager is reviewing the financial status of her project. The Estimate at Completion (EAC) is $500,000, and the Actual Cost (AC) to date is $300,000. What is the Estimate to Complete (ETC) for this project?

  • $200,000

  • $300,000

  • $800,000

  • $500,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.