A project manager is reviewing the mechanisms installed for tracking the anticipated benefits of a new software implementation project. Which of the following would BEST verify that an effective measurement system is in place?
Reviewing the project charter to ensure alignment with strategic goals
Utilizing statistical analysis tools to assess the efficacy and accuracy of collected data
Implementing automated tracking systems in project management software
Scheduling regular team meetings to discuss the perceived benefits of the project