Free PMI Project Management Professional (PMP) Practice Question

A project manager is reviewing the project's performance and needs to calculate the Estimate at Completion (EAC). The project has a Budget at Completion (BAC) of $500,000, and the current Cost Performance Index (CPI) is 0.8. Which of the following represents the most likely EAC assuming the current performance trend continues?

  • $625,000

  • $550,000

  • $500,000

  • $400,000

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.