A project manager is using PERT to estimate the duration of a critical activity. The optimistic estimate is 4 days, the most likely estimate is 6 days, and the pessimistic estimate is 14 days. What is the expected duration (TE) of this activity?

  • 7 days

  • 9 days

  • 8 days

  • 6 days