Free PMI Project Management Professional (PMP) Practice Question

A project manager is using PERT to estimate the duration of an activity. The optimistic estimate is 4 days, the most likely estimate is 6 days, and the pessimistic estimate is 14 days. What is the expected duration (TE) for this activity?

  • 9 days

  • 7 days

  • 6 days

  • 8 days

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.