A project manager is using the Critical Path Method (CPM) to analyze a project schedule. They find that Activity X has an Early Start (ES) of 10 days and a Late Start (LS) of 15 days. What is the float for Activity X?

  • 25 days

  • 15 days

  • 5 days

  • 10 days