Free PMI Project Management Professional (PMP) Practice Question

A project manager is using the PERT technique to estimate the duration of a critical activity. The optimistic estimate is 10 days, and the pessimistic estimate is 22 days. What is the standard deviation for this activity?

  • 1 day

  • 3 days

  • 2 days

  • 4 days

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.