A project manager is using Three-Point Estimation to calculate the expected duration of a critical activity. The optimistic estimate is 10 days, the most likely estimate is 14 days, and the pessimistic estimate is 22 days. What is the expected duration (TE) of this activity?
14 days
15.33 days
14.67 days
16 days