A project manager is using three-point estimation to calculate the variance for a critical project activity. The optimistic estimate is 10 days, and the pessimistic estimate is 22 days. What is the variance for this activity?

  • 2 days²

  • 4 days²

  • 36 days²

  • 12 days²