Free PMI Project Management Professional (PMP) Practice Question

A project manager is working on a construction project and notices that the resource histogram shows significant peaks and valleys in the workload for skilled laborers. Which technique should the project manager apply to address this issue without changing the project's critical path or completion date?

  • Fast tracking

  • Resource smoothing

  • Crashing the schedule

  • Resource leveling

This question's topic:
PMI Project Management Professional (PMP) / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.