A project manager is working on a project that has shifted from a predominantly predictive approach to incorporating more agile practices. According to the PMI's Agile Practice Guide, what is a key factor the project manager should consider to increase the success of this transition?

  • Aligning the project practices with the organizational culture

  • Increasing the level of documentation to ensure comprehensive coverage

  • Eliminating customer collaboration to streamline decision-making

  • Reducing the frequency of team meetings to allow more focused work