To determine the risk score, we multiply the probability by the impact for each risk:
Risk 1: 0.3 x 0.5 = 0.15 Risk 2: 0.6 x 0.2 = 0.12
The first risk has a score of 0.15, which is higher than the second risk's score of 0.12. This demonstrates that a risk with lower probability can still have a higher overall risk score if its impact is significantly higher. Understanding how to calculate and compare risk scores is crucial for prioritizing risks and developing appropriate response strategies in project management.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
How do you calculate a risk score in project management?
Open an interactive chat with Bash
What does it mean when a risk has a higher impact but lower probability?
Open an interactive chat with Bash
Why is it important to understand risk scores when managing projects?
Open an interactive chat with Bash
This question's topic:
PMI Project Management Professional (PMP) /
Process
Report Issue
Oh snap!
Loading...
Loading...
Join premium for unlimited access and more features