Free PMI Project Management Professional (PMP) Practice Question

After a series of training sessions aimed at improving project risk management techniques, you intend to measure the impact of the training on your project team’s performance. Which of the following methods provides the most direct evidence of the enhancement in their skills and the training's effectiveness?

  • Evaluating the improvement in risk management outcomes through documented lessons learned from recent project phases

  • Comparing the cost of training versus the financial impact on the project’s budget

  • Conducting a survey to gather the project team’s feedback on the training content and trainer effectiveness

  • Reviewing the attendance records of the team members who participated in the training sessions

This question's topic:
PMI Project Management Professional (PMP) / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.