An agile team seeks to enhance their sprint planning by accurately forecasting how much product backlog work they can likely accomplish in the next sprint. Which metric would provide the best foundation for their sprint capacity planning?
Burn-up chart
Burn-down chart
Cumulative flow diagram
Velocity