As a project manager for a multinational infrastructure project, you received a weekly status report from the construction team that highlighted several critical issues which were not communicated to the relevant stakeholders yet. What should be your FIRST action in line with the best practices of Manage Communications?

  • Escalate issues in the report to senior management for feedback and prioritization.

  • Postpone the communication of these issues until they are resolved to avoid unnecessary concerns among stakeholders.

  • Archive the status report until the following weekly stakeholder meeting to present all issues collectively.

  • Evaluate the urgency of the issues reported and identify the appropriate stakeholders for communication as per the communications management plan.