Free PMI Project Management Professional (PMP) Practice Question

As a project manager in charge of a new infrastructure project, you are drafting the Cost Management Plan. During this process, which of the following should you incorporate to best ensure that the plan aligns with the knowledge and expectations of key stakeholders?

  • A fixed cost estimate that can only be adjusted with stakeholder approval in accordance with the Waterfall Methodology

  • An immutable assumption log

  • Stakeholder engagement to incorporate their knowledge and expectations

  • Project funding requirements

This question's topic:
PMI Project Management Professional (PMP) / 
Waterfall
Your Score:

Check or uncheck an objective to set which questions you will receive.